Current lead-time per 16 November 2018

Component Lead time
Tyres 7 days
Light Systems 5 days
Mirror/ Glass 5 days
Passive Safety 20 days
EMC/ Electrical devices 15 days
Emissions (component) 15 days
Heat/ Cleaning/ Flam./ Brake 10 days
Coupling/ Protection 10 days
Noise 5 days
LPG/ CNG/ H2 10 days
WVTA/Systems Lead time
WVTA/Systems M1/N1/L/O1-2 30 days
WVTA/Systems M2-M3/N2-N3/T/O3-O4 30 days

* Calendar days