Current lead-time per 10 January 2020

Component Lead time
Tyres 31 days
Light Systems 8 days
Mirror/ Glass 8 days
Passive Safety 8 days
EMC/ Electrical devices 18 days
Emissions (component)39 days
Heat/ Cleaning/ Flam./ Brake 5 days
Coupling/ Protection 5 days
Noise 30 days
LPG/ CNG/ H2 25 days
WVTA/Systems Lead time
WVTA/Systems M1/N1/L/O1-2 35 days
WVTA/Systems M2-M3/N2-N3/T/O3-O4 40 days

* Calendar days